Interior trim is next for the Washington Park Remodel
Here are a few images of the progress. The soffit detail has been completed, integrating the addition with the house. The leaded glass...

Ellen Mirro
Jan 13, 20121 min read
Â
Â
Â


Progress at the Washington Park Remodel
Drywall will be hung next week with cabinetry and trim work to follow… The last window will be installed once the tub has been moved into...

Ellen Mirro
Dec 29, 20111 min read
Â
Â
Â


Richmond Beach Addition Progress
Windows, siding, and drywall are in! Finishes are starting to be installed. With the siding on, it is starting to look finished on the...

Ellen Mirro
Dec 5, 20111 min read
Â
Â
Â


Washington Park Remodel Update
The last of the demolition happens this week with the removal of the old un-used brick chimneys. Framing of the remodel should be...

Ellen Mirro
Nov 30, 20111 min read
Â
Â
Â


Framing nears completion on the Richmond Beach Addition.
Now that demolition is complete the framing seems to be going quite quickly. The porch and eave make a big difference. The new entry off...

Ellen Mirro
Sep 21, 20111 min read
Â
Â
Â


Nearing Completion
The new porch and dormer addition in Loyal Heights is nearing completion. Check out these pictures… The Trellis is being installed. Final...

Ellen Mirro
Sep 14, 20111 min read
Â
Â
Â


Progress on the Maple Creek Kitchen
We have been working on a kitchen for a midcentury modern house by Maple Creek in North Seattle. It is turning out great and should be...

Ellen Mirro
Aug 29, 20111 min read
Â
Â
Â


Loyal Heights project nearing completion
Here are a few pictures. (next time we post this project it will be finished.) Final stucco coat, paint and assemble trellis, then...

Ellen Mirro
Aug 23, 20111 min read
Â
Â
Â


Construction has begun on our Richmond Beach Addition project
Here are a couple photos to give you a feel for place. Stucco removed to be replaced with shingles, and a porch across the whole south...

Ellen Mirro
Aug 11, 20111 min read
Â
Â
Â


The Loyal Heights Addition is nearing completion
The final items are all that remain to completing the Loyal Heights Addition. The sunroom windows have been installed and trimmed. Once...

Ellen Mirro
Aug 9, 20111 min read
Â
Â
Â


Loyal Heights Progress
The bathroom is being tiled and trimmed. The exterior is ready for Stucco and handrail. Ready for tile, columns, and balustrade. Ready...

Ellen Mirro
Jul 20, 20111 min read
Â
Â
Â


An update for the OutWest Bar in West Seattle
The existing building is undergoing an interior remodel to convert it to an assembly 2 type space, suitable for an eating and drinking...

Ellen Mirro
Jul 12, 20111 min read
Â
Â
Â


Progress on OutWest Bar in West Seattle
We assisted the owners of the OutWest Bar in West Seattle with both Construction and Master Use Permits. They are now under construction,...

Ellen Mirro
Jun 28, 20111 min read
Â
Â
Â


A kitchen remodel comes together.
The cabinets are in and the counters are being installed. It should be finished soon. The buffet cabinet will have beveled glass doors in...

Ellen Mirro
Jun 3, 20111 min read
Â
Â
Â


The Bonnie View Porch Addition
It is waiting on the weather to be painted… will we ever get a stretch of dry weather? The porch blends in nicely with the home. The...

Ellen Mirro
Jun 2, 20111 min read
Â
Â
Â


The Loch-Gilvra Dormer Addition is ready for stucco
The remodel is in its final stages and should be wrapped up later this month. The dormer addition is ready for stucco. The interior is...

Ellen Mirro
Jun 2, 20111 min read
Â
Â
Â


Loyal Heights Addition Progresses
The dormer for the bathroom and the deck have been framed up. The spaces will continue to get more defined in the weeks to come. The deck...

Ellen Mirro
May 25, 20111 min read
Â
Â
Â


Work progresses on the Loyal Heights Addition
Here are a couple pictures of the construction progress. Construction access to the dormer addition is on the exterior. Concrete gets...

Ellen Mirro
May 10, 20111 min read
Â
Â
Â


Foundations for a new balcony
Part of our services include observing the construction progress of the project. These footings are being poured in segments to preserve...

Ellen Mirro
May 6, 20111 min read
Â
Â
Â


Loch Gilvra Dormer Addition
The dormer is framed, and the massing is appropriate for an older home. The size of the dormer as seen from the street. #Dormer #Remodel

Ellen Mirro
Apr 20, 20111 min read