Framing nears completion on the Richmond Beach Addition.

  • Writer: Ellen Mirro
    Ellen Mirro
  • Sep 21, 2011
  • 1 min read

Now that demolition is complete the framing seems to be going quite quickly.

The porch and eave make a big difference.


The new entry off the dining room open to the yard nicely.


The new floor joists are 4x6s to match the thickness of the existing framing.


The round window will be a little larger than this.


The master bath bump out will accommodate a toilet and large tub.